Question: Consider the following work breakdown structure: Given a due date of 210 days, what is the earliest you can start activity D without delaying the

Consider the following work breakdown structure:

Consider the following work breakdown structure: Given a due date of 210 days, what is the earliest you can start activity D without delaying the project? Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B C,D D OL OOOOO