Question: Consider the following work breakdown structure: Start Finish Time Estimates (wks) Activity Node Node to tm tp 223 ABCDE 1 2 11 20 3 2

Consider the following work breakdown structure: Start Finish Time Estimates (wks) Activity Node Node to tm tp 223 ABCDE 1 2 11 20 3 2 5 4 18 30 42 4 7 10 13 1 4 31 40 43 23 29 8 What is the estimated standard deviation in the time for activity E? Multiple Choice 3 weeks 4 weeks 2 weeks O week 1 week