Question: Consider the following work breakdown structure: Start Finish Time Estimates(wks) Activity Node Node to tm tp A 1 2 11 20 29 B 2 3
Consider the following work breakdown structure:
Start Finish Time Estimates(wks)
Activity Node Node to tm tp
A 1 2 11 20 29
B 2 3 2 5 8
C 2 4 18 30 42
D 3 4 7 10 13
E 1 4 31 40 43
What is the estimated expected (mean) time for activity E?