Question: Consider the following work breakdown structure: tp Activity A B Start Finish Node Node 1 2 2 3 2 4 3 4 1 4 Time
Consider the following work breakdown structure: tp Activity A B Start Finish Node Node 1 2 2 3 2 4 3 4 1 4 Time Estimates (wks) to tm 11 20 29 2 5 8 18 30 42 7 10 13 31 40 43 D E What is the estimated standard deviation in the time for activity E