Question: Consider the following work breakdown structure: table [ [ , table [ [ Start ] , [ Activity ] ] , table

Consider the following work breakdown structure:
\table[[,\table[[Start],[Activity]],\table[[Finish],[Node]],\table[[Duration (days)],[Node]],Optimistic,Most Likely,Pessimistic],[A,1,2,41,50,59,,,,],[B,1,3,54,60,66,,,,],[C,2,4,58,70,82,,,,],[D,3,4,32,41,44,,,,]]
What is the estimated expected (mean) time for activity D?
 Consider the following work breakdown structure: \table[[,\table[[Start],[Activity]],\table[[Finish],[Node]],\table[[Duration (days)],[Node]],Optimistic,Most Likely,Pessimistic],[A,1,2,41,50,59,,,,],[B,1,3,54,60,66,,,,],[C,2,4,58,70,82,,,,],[D,3,4,32,41,44,,,,]] What is