Question: Consider the following work breakdown structure: to to N Activity A B 2. Start Finish Node Node 1 2 3 2 4 3 4 1

Consider the following work breakdown structure:Consider the following work breakdown structure:

Consider the following work breakdown structure: to to N Activity A B 2. Start Finish Node Node 1 2 3 2 4 3 4 1 4 3 mon00D Time Estimates (wks) tm 11 20 29 2 5 8 18 30 42 7 10 13 31 40 43 PWN E + What is the estimated expected (mean) time for activity E? Multiple Choice 31 weeks 38 weeks 39 weeks 40 weeks O 43 weeks