Question: Quantitative Question ( Write legibly; Credit will be given only if appropriate work is done. ) Consider the following work breakdown structure for a project:

Quantitative Question (Write legibly; Credit will be given only if appropriate work is done.)

Consider the following work breakdown structure for a project:

Activity Start Node Finish Node Optimistic Time Most Likely Time Pessimistic Time
A 1 2 51 60 59
B 1 3 54 60 76
C 2 4 58 70 82
D 3 4 32 48 44

5

What is the probability that this project will be completed within 135 days?