Question: Consider the following work breakdown structure: table [ [ , , Time Estimates ( days ) ] , [ Activity , Precedes,Optimistic,Most Likely,Pessimistic ]

Consider the following work breakdown structure:
\table[[,,Time Estimates (days)],[Activity,Precedes,Optimistic,Most Likely,Pessimistic],[Start,A, B,-,-,-],[A,C, D,44,50,56],[B,D,45,60,75],[C,E,42,45,48],[D,F,31,40,49],[E,F,27,36,39],[F,End,58,70,82]]
What is the estimated slack time for activity D?
 Consider the following work breakdown structure: \table[[,,Time Estimates (days)],[Activity,Precedes,Optimistic,Most Likely,Pessimistic],[Start,A, B,-,-,-],[A,C,