Question: Consider the following work breakdown structure: 50 Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C 38 62 E 79 115 115 End

Consider the following work breakdown structure:
Consider the following work breakdown structure: 50 Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C 38 62 E 79 115 115 End 85 100 115 F 19 25 31 E End 91 100 115 F End 62 65 68 What is the probability that this project will NOT be completed within 205 days? 0.0823 0.8413 0.9177 0.7549 0.2451