Question: Consider the following work breakdown structure: table [ [ , Time Estimates ( days ) ] , [ Activity , Precedes,Optimistic,Most Likely,Pessimistic ] ,
Consider the following work breakdown structure:
tableTime Estimates daysActivityPrecedes,Optimistic,Most Likely,PessimisticStartA B CADBECEnd,DFEEnd,FEnd,
What is the estimated expected mean time for project completion?
Learning Objective: Analyze networks with probabilistic times.
days
days
days
days
days