Question: Consider the following work breakdown structure: table [ [ , Time Estimates ( days ) ] , [ Activity , Precedes,Optimistic,Most Likely,Pessimistic ] ,

Consider the following work breakdown structure:
\table[[,Time Estimates (days)],[Activity,Precedes,Optimistic,Most Likely,Pessimistic],[Start,A, B, C,-,-,-],[A,D,38,50,62],[B,E,90,99,108],[C,End,85,100,115],[D,F,19,25,31],[E,End,91,100,115],[F,End,62,65,68]]
What is the estimated expected (mean) time for project completion?
Learning Objective: 17-08 Analyze networks with probabilistic times.
100 days
140 days
199 days
200 days
440 days
 Consider the following work breakdown structure: \table[[,Time Estimates (days)],[Activity,Precedes,Optimistic,Most Likely,Pessimistic],[Start,A, B,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!