Question: Consider the following work breakdown structure: table [ [ , , Duration Estimates ] , [ Activity , Precedes,Optimistic,Most Likely,Pessimistic ] , [ Start

Consider the following work breakdown structure:
\table[[,,Duration Estimates],[Activity,Precedes,Optimistic,Most Likely,Pessimistic],[Start,U,V,-,-,-],[U,W,35,50,65],[V,W, X,28,40,52],[W,Z,26,35,44],[X,Y,28,40,52],[Y,Z,26,29,38],[Z,End,36,60,84]]
What is the estimated expected (mean) time for project completion?
 Consider the following work breakdown structure: \table[[,,Duration Estimates],[Activity,Precedes,Optimistic,Most Likely,Pessimistic],[Start,U,V,-,-,-],[U,W,35,50,65],[V,W, X,28,40,52],[W,Z,26,35,44],[X,Y,28,40,52],[Y,Z,26,29,38],[Z,End,36,60,84]] What

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!