Question: Consider the following work breakdown structure: 7 Duration (days) Activity A Preceding Task 44:52 Optimistic 41 Pessimistic 59 B 54 Most Likely 50 60 70

Consider the following work breakdown structure:

Consider the following work breakdown structure: 7 Duration (days) Activity A Preceding Task 44:52 Optimistic 41 Pessimistic 59 B 54 Most Likely 50 60 70 41 66 58 D B 32 82 44 es What is the probability that this project will be completed within 130 days? Multiple Choice 8413 O .90 O 9544 9772 O