Question: Consider the following work breakdown structure Time Estimaton (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, A D 38 50 62 B E

Consider the following work breakdown structure
Consider the following work breakdown structure Time Estimaton (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, A D 38 50 62 B E 90 99 108 C End 85 100 115 D 19 25 31 E End 91 100 115 F End 62 65 69 05 What is the probability that this project will be completed within 205 days? Multiple Choice 972 9544 IMO