Question: Consider the following work breakdown structure: table [ [ , Start,Finish,Time,Estimates ( wks ) ] , [ Activity , Node,Node, t 0 , t

Consider the following work breakdown structure:
\table[[,Start,Finish,Time,Estimates(wks)],[Activity,Node,Node,t0,tm,tp,,],[A,1,2,11,20,29,,],[B,2,3,2,5,8,,],[C,2,4,18,30,42,,],[D,3,4,7,10,13,,],[E,1,4,31,40,43,,]]
What is the estimated expected (mean) time for activity E?
 Consider the following work breakdown structure: \table[[,Start,Finish,Time,Estimates(wks)],[Activity,Node,Node,t0,tm,tp,,],[A,1,2,11,20,29,,],[B,2,3,2,5,8,,],[C,2,4,18,30,42,,],[D,3,4,7,10,13,,],[E,1,4,31,40,43,,]] What is the estimated