Question: Consider the following work breakdown structure: 54 Start Finish Duration (days) Activity Node Node Optimistic Most Likely Pessimistic A 1 2 41 50 59 B

Consider the following work breakdown structure:

Consider the following work breakdown structure: 54 Start Finish Duration (days) Activity Node Node Optimistic Most Likely Pessimistic A 1 2 41 50 59 B 1 3 59 66 2 4 58 70 82 D 3 4 32 41 44 E 4 5 78 F 6 30 36 G 5 7 44 49 62 H 6 7 32 40 41 What is the estimated expected (mean) time for project completion? (Keep 1 decimal place) 73 60 25