Question: Consider the following work breakdown structure: Time Estimates ( days ) Activity Precedes Optimistic Most Likely Pessimistic table [ [ Start , A ,

Consider the following work breakdown structure:
Time Estimates (days)
Activity Precedes Optimistic Most Likely Pessimistic
\table[[Start,A,B,-,-,-],[A,C,D,44,50,56],[B,D,45,60,75],[C,E,42,45,48],[D,F,31,40,49],[E,F,27,36,39],[F,End,58,70,82]]