Question: Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C - - - A D 37 49 61
Consider the following work breakdown structure:
| Time Estimates (days) | ||||||||||
| Activity | Precedes | Optimistic | Most Likely | Pessimistic | ||||||
| Start | A,B,C | - | - | - | ||||||
| A | D | 37 | 49 | 61 | ||||||
| B | E | 80 | 95 | 98 | ||||||
| C | End | 91 | 100 | 115 | ||||||
| D | F | 23 | 25 | 51 | ||||||
| E | End | 42 | 48 | 66 | ||||||
| F | End | 62 | 65 | 80 | ||||||
What is the estimated expected (mean) time for project completion? Show your work!
| A | 143 days |
| B | 382 days |
| C | 150 days |
| D | 145 days |
| E | 389 day |