Question: Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C - - - A D 38 50 62

Consider the following work breakdown structure:

Time Estimates (days)
Activity Precedes Optimistic Most Likely Pessimistic
Start A,B,C - - -
A D 38 50 62
B E 83 86 107
C End 85 100 115
D F 19 25 31
E End 91 100 115
F End 62 65 68

What is the probability that this project will be completed within 205 days?

A

0.9960

B

0.9996

C

0.9993

D

0.9544

E

0.8413