Question: Consider the following work breakdown structure: What is the probability of finishing the project at exactly 201 days? Time Estimates (days) Activity Precedes Optimistic Most

Consider the following work breakdown structure: What is the probability of finishing the project at exactly 201 days? Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start AB C,D End 1909998
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
