Question: Consider the following work breakdown structure: What is the probability that the project will be finished within 221 days? Time Estimates (days) Activity Precedes Optimistic

Consider the following work breakdown structure: What is the probability that the project will be finished within 221 days?

Time Estimates (days)

Activity

Precedes

Optimistic

Most Likely

Pessimistic

Start

A,B

-

-

-

A

C,D

44

50

56

B

D

45

60

75

C

E

42

45

48

D

F

31

40

49

E

F

27

36

39

F

End

58

70

82

a.1.

b.0.

c.0.9.

d.0.6.

e.2.5.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!