Question: Consider the following work breakdown structure: What is the probability of finishing the project at exactly 201 days? Time Estimates (days) Optimistic Most Likely Pessimistic

Consider the following work breakdown structure:
Consider the following work breakdown structure: What is the probability of finishing the project at exactly 201 days? Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start A B Precedes AB CD D E F F End D E F 44 45 42 31 27 58 50 60 45 40 36 20 56 75 48 49 39 82 0 016 215

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To solve this problem well use the Program Evaluation and Review Technique PERT which involves calculating the expected duration and variance for each ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!