Question: Consider the following workbreakdown structure: Activity Precedes Duration (weeks) Start a, e 0 a cd 4 e f 9 f B 5 d B 2

Consider the following workbreakdown structure:
Consider the following workbreakdown structure: Activity Precedes Duration (weeks) Start a, e 0 a cd 4 e f 9 f B 5 d B 2 c end 6 B end 3 When is the latest we can start activities cd, and f, respectively and still complete the project on time? O a 17. 12, and 9 weeks, respectively b.4, 13. and 9 weeks, respectively none of the answers presented 08.11.17 and 9 weeks, respectively 2.4.4 and 9 weeks, respectively