Question: Activity Precedes Duration (weeks) Start a, e 0 a cd 4. e f f g 5 f d 8 w O N D C end

Activity Precedes Duration (weeks) Start a, e 0 a
Activity Precedes Duration (weeks) Start a, e 0 a cd 4. e f f g 5 f d 8 w O N D C end 6 ho end What is the project duration? O a. 14 weeks O b. 17 weeks O C. 10 weeks d. none of the answers presented e. 13 weeks