Question: Consider the information below for a given project, activity times are in days. Determine: The probability of completing the project within 20 days The probability
Consider the information below for a given project, activity times are in days. Determine:
- The probability of completing the project within 20 days
- The probability of completing the project between 17 and 21 days
- The probability of completing the project within 16 days
- The number of days to complete the project within a probability of 95%
| Activity | A | M | B | Immediate Predecessors |
| A | 1 | 2 | 3 | - |
| B | 2 | 3 | 4 | - |
| C | 4 | 5 | 6 | A |
| D | 8 | 9 | 10 | B |
| E | 2 | 5 | 8 | C,D |
| F | 4 | 5 | 6 | B |
| G | 1 | 2 | 3 | E |