Question: Consider the information below for a given project, activity times are in days. Determine: The probability of completing the project within 20 days The probability

Consider the information below for a given project, activity times are in days. Determine:

  1. The probability of completing the project within 20 days
  2. The probability of completing the project between 17 and 21 days
  3. The probability of completing the project within 16 days
  4. The number of days to complete the project within a probability of 95%

Activity

A

M

B

Immediate Predecessors

A

1

2

3

-

B

2

3

4

-

C

4

5

6

A

D

8

9

10

B

E

2

5

8

C,D

F

4

5

6

B

G

1

2

3

E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!