Question: Consider the following network for a small project (all times are in days). Most Activity Pred. Optimistic Pessimistic Likely start 1 3 N B start

Consider the following network for a small

Consider the following network for a small project (all times are in days). Most Activity Pred. Optimistic Pessimistic Likely start 1 3 N B start 4 6 5 . 1 3 2 D B 7 15 8 E 4 6 5 F C 6 14 9 9 G DF 2 4 3 I I E 6 12 10 Use PERT to determine the critical path and associated time. The customer wants the project delivered in 20 days. What is the probability of meeting the customer's expectation