Question: Consider the MPS, BOM, and inventory data shown. Master Production Schedule: The following table shows the MPS start quantities for the next 10 weeks. Bill

Consider the MPS, BOM, and inventory data shown. Master Production Schedule: The following table shows the MPS start quantities for the next 10 weeks. Bill of Material: - Item A uses 2 each of component D,1 each of component C and 2 each of subassembly B. - Subassembly B uses 2 each of component E. Selected Inventarv Data Construct the MRP schedule using the preceding information. Blank MRP records are provided at the end of this test