Question: 7. (25 points) Consider the MPS, BOM, and inventory data shown. Master Production Schedule: The following table shows the MPS start quantities for the next

7. (25 points) Consider the MPS, BOM, and7. (25 points) Consider the MPS, BOM, and

7. (25 points) Consider the MPS, BOM, and inventory data shown. Master Production Schedule: The following table shows the MPS start quantities for the next 6 weeks. Finished Item A 1 2 3 4 5 6 MPS Start 20 40 30 20 Bill of Material: - Item A uses 1 each of subassembly C and 2 each of subassembly B. - 1 subassembly B uses 2 each of component D. - 1 subassembly C uses 3 each of component D. d. (11 points) Complete the following MRP record for Item D: Item: D Lot size: MULT 50 Lead time: 1 week Weeks 1 2 3 4 5 6 Gross requirements Scheduled receipts Projected on hand 200 Net Requirements Planned order receipts Planned order releases

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!