Question: Consider the network described in the table below. Calculate the expected duration of each activity. (6 marks) Calculate the expected duration and variance of the
Consider the network described in the table below.
- Calculate the expected duration of each activity. (6 marks)
- Calculate the expected duration and variance of the critical path. (2 marks)
- Calculate the probability that the project will be completed in more than 28 weeks time units. (2 marks)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
