Question: Consider the network described in the table below. Most Immediate Optimistic Likely Pessimistic Activity Predecessor(s) Time (days) Time (days) Time (days) A none 5 8

Consider the network described in the table below. Most Immediate Optimistic Likely Pessimistic Activity Predecessor(s) Time (days) Time (days) Time (days) A none 5 8 17 B none 7 10 13 C A 3 5 7 D A 1 3 5 G B,D 4 6 8 E B,D 3 3 3 F C,E 2 3 7 What is the probability that the project can be completed in 19 days or less Group of answer choices

about 42%

about 22%

about 58%

78%