Question: The following table represents a project with four activities. All times are in weeks. Using the data in the table, what is the critical path?
The following table represents a project with four activities. All times are in weeks. Using the data in the table, what is the critical path? Question 16 options: A-B A-B-C-D B-D A-C None of the above

Most Immediate Optimistic Likely Pessimistic Activity Predecessor Time Time Time A 2 8 14 B 8 8 8 C A 6 9 18 D B 5 11 17 Using the data in the table, what is the critical path? A-B A-B-C-D OB-D A-C ONone of the above Screenshot