Question: Consider the network presented in the following table. Calculate a . All possible paths b . The critical path c . The slack available at

Consider the network presented in the following table. Calculate
a. All possible paths
b. The critical path
c. The slack available at any non-critical points
d. The minimum project duration
\table[[,,Immediate],[Task,Duration (Days),Predecessors],[A,5,None],[B,3,A],[C,4,A],[D,2,C],[E,1,B,D]]