Question: Consider the network presented in the following table Calculate A) All Possible Paths B) The Critical Path C) The Slack Available At Any Non Critical
Consider the network presented in the following table
Calculate
A) All Possible Paths
B) The Critical Path
C) The Slack Available At Any Non Critical Points
D) The Minimum Project Duration
| Task | Duration (Days) | Immediate Predecessors |
| A | 5 | None |
| B | 7 | A |
| C | 4 | A |
| D | 2 | C |
| E | 1 | B,D |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts