Question: Consider the PERT time estimates: Activity Immediate Predecessors a m b A 2 5 9 B A 1 6 8 C A 3 5 12
- Consider the PERT time estimates:
Activity Immediate
Predecessors a m b
A 2 5 9
B A 1 6 8
C A 3 5 12
D B 2 4 12
E B, C 4 6 8
F B 6 7 8
G D, E 1 2 6
H F, G 4 6 16
Draw a network for this project and determine the critical path based on the most likely times by inspection.
- Which of the following is the critical path?
- A-C-E-G-H
- A-B-F-H
- A-B-E-G-H
- A-B-G-H
- What is the expected path length?
- What is the variance of the path length?
- What is the probability that the project will be completed before 28 weeks (in decimal value)?
- What is the probability that the project will be completed before 32 weeks (in decimal value)?
- Assuming the critical path identified using the most likely times, how many days are required to complete the project with probability of 95%?