Question: Consider the precedence chart given below. Give the sequence of crashing for 5 days. Compute the extra cost incurred because of crashing by 5 days.
Consider the precedence chart given below. Give the sequence of crashing for 5 days. Compute the extra cost incurred because of crashing by 5 days.
| Activity | Immediate Predecessors | Normal Time (days) | Crash Time (days) | Normal Cost $ | Crash Cost $ |
| A | - | 4 | 2 | 200 | 500 |
| B | - | 3 | 3 | 300 | 300 |
| C | A,B | 6 | 2 | 800 | 1200 |
| D | - | 4 | 3 | 400 | 600 |
| F | D | 8 | 5 | 1000 | 1600 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock