Question: Consider the precedence chart given below. Give the sequence of crashing for 5 days. Compute the extra cost incurred because of crashing by 5 days.

Consider the precedence chart given below. Give the sequence of crashing for 5 days. Compute the extra cost incurred because of crashing by 5 days.

Activity Immediate Predecessors

Normal Time

(days)

Crash Time

(days)

Normal Cost

$

Crash Cost

$

A - 4 2 200 500
B - 3 3 300 300
C A,B 6 2 800 1200
D - 4 3 400 600
F D 8 5 1000 1600