Question: Consider the project as outline in the tables below: Activity Predecessor Normal Time Crash Time (wks) Normal Cost (S/wk) 1000 Cost to Crash (s/wk) 2200

Consider the project as outline in the tables

Consider the project as outline in the tables below: Activity Predecessor Normal Time Crash Time (wks) Normal Cost (S/wk) 1000 Cost to Crash (s/wk) 2200 500 900 250 350 300 800 400 700 1500 800 1500 2500 2500 4000 A. Crash the project to its minimum. What is the minimum crashing time? B. What is the total crashing cost? C. Assuming that the indirect cost is $ 8000, What is the total project cost after crashing