Question: please answer a),b),c) NOV 174 3-Consider the project as outline in the tables below: Activity Predecessor Normal Time Crash (wks) Time (wks) 16 8 Cost
please answer a),b),c)
NOV 174 3-Consider the project as outline in the tables below: Activity Predecessor Normal Time Crash (wks) Time (wks) 16 8 Cost to Crash ($/wk) Normal Cost (S/wk) 1000 A 2200 B 14 9 500 900 C A 8 6 250 350 5 D A 4 300 700 E B 4 2 800 1500 F B 6 4 400 800 G 10 7 1500 2500 H D, E 15 10 2500 4000 A. Crash the project to its minimum. What is the minimum crashing time? B. What is the total crashing cost? C. Assuming that the indirect cost is $ 8000, What is the total project cost after crashing