Question: Consider the project below. The earliest start time is 0 . You can assume Basic PERT probabilities. Task ID Predecessor Best Case Most Likely Worst

Consider the project below. The earliest start time is 0. You can assume Basic PERT probabilities.
Task ID
Predecessor
Best Case
Most Likely
Worst Case
1
-
9
13
18
2
1
9
11
17
3
1
9
13
19
4
2
9
16
25
5
2
11
14
21
6
3,4,5
8
11
14
7
6
14
20
25
What is the expected completion time of the project to the nearest integer in days?