Question: Consider the project below. The earliest start time is 0 . You can assume Basic PERT probabilities. Task IDPredecessorBest CaseMost LikelyWorst Case 1 - 9

Consider the project below. The earliest start time is 0. You can assume Basic PERT probabilities. Task IDPredecessorBest CaseMost LikelyWorst Case1-913182191117319131942916255211142163,4,58111476142025 What is the critical path of the project based on expected times