Question: Consider the project below. The earliest start time is 0 . You can assume Basic PERT probabilities. Task ID Predecessor Best Case Most Likely Worst

Consider the project below. The earliest start time is 0. You can assume Basic PERT probabilities.
Task ID
Predecessor
Best Case
Most Likely
Worst Case
1
-
9
13
18
2
1
9
11
17
3
1
9
13
19
4
2
6
11
22
5
2
11
14
21
6
3,4,5
8
11
14
7
6
14
20
25
Provide quote a completion time for this project with at least 95 percent confidence:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!