Question: Consider the project dependency matrix and activity durations provided below. Find the critical path. A1 A2 A4 A5 A6 A1 A2 A3 A4 A5 X

Consider the project dependency matrix and

Consider the project dependency matrix and activity durations provided below. Find the critical path. A1 A2 A4 A5 A6 A1 A2 A3 A4 A5 X A6 Duration 5 4 3 4 2 4 O a. None of the other answers are correct. O b. A1-A2-A3-A6 O C. A1-A5-A6 O d. A1-A4-A5-A6