Question: Consider the project described in problem 3 . Suppose that the activity times are random variables with a constant coefficient of variation of 0 .
Consider the project described in problem Suppose that the activity times are random
variables with a constant coefficient of variation of The coefficient of variation is
the ratio Assume that the times given in problem are the mean activity times.
a Compute the standard deviation of each of the activity times.
b Find the mean and the variance of the path with the longest expected completion time.
c Using the results of part b estimate the probability that the project is completed
within weeks.
d Using the results of part b estimate the number of weeks required to complete the
project with probability