Question: Consider the project information in the table (time in weeks) Activity Immediate Predecessor a m b A -- 5 10 15 B A 11 15
Consider the project information in the table (time in weeks)
| Activity | Immediate Predecessor | a | m | b |
| A | -- | 5 | 10 | 15 |
| B | A | 11 | 15 | 19 |
| C | A | 13 | 17 | 21 |
| D | B, C | 14 | 16 | 21 |
| E | C | 8 | 18 | 22 |
| F | D | 9 | 13 | 17 |
| G | E, F | 6 | 11 | 16 |
- Construct the PERT network diagram for this project.
- Compute the mean and variance in time for each activity
- Find the critical path and determine the expected length of the critical path?
- Assuming normality and path independence, what is the probability of meeting the 72-week deadline?