Question: Consider the project network described in the table below where time estimates are given in weeks. If activity K is delayed by six weeks, what

Consider the project network described in the table below where time estimates are given in weeks.

Consider the project network described in the

If activity K is delayed by six weeks, what would happen to the expected project duration?

a.) Project duration increases by 1 week.

b.) No change in project duration.

c.) Project duration increases by 6 weeks.

d.) Project duration increases by 0.5 weeks.

Activity Immediate Predecessor(s) J K L J M J N KM 0 KM P LAN Pessimistic Most Likely Optimistic Expected Variance Duration 15 10 8 ? ? 9 8 7 8 0.11 10 6 5 6.5 0.69 3 3 3 3 0 9 5 1 5 1.78 10 7 4 7 10 8 3 7.5 1.36 P N End Start M O K

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!