Question: Consider the project network described in the table below where time estimates are given in weeks. What is the likelihood of the project being completed

Consider the project network described in the table below where time estimates are given in weeks.

Consider the project network described in the

What is the likelihood of the project being completed by a deadline of 25 weeks?

a.) 74%

b.) 26%

c.) 32%

d.) 10%

Activity Immediate Predecessor(s) J K L J M J N KM 0 KM P LAN Pessimistic Most Likely Optimistic Expected Variance Duration 15 10 8 ? ? 9 8 7 8 0.11 10 6 5 6.5 0.69 3 3 3 3 0 9 5 1 5 1.78 10 7 4 7 10 8 3 7.5 1.36 P N End Start M O K