Question: Consider the project network given below: Numbers along the arcs represent: crash time ( days ) , normal time ( days ) per unit cost
Consider the project network given below:
Numbers along the arcs represent: crash time days normal time days per unit cost of crashing $ Note: jobs A and cannot be crashed.
a Use the direct enumeration method to determine the least cost crashing schedule that will meet the project deadline of days. What is the total crashing cost?
b Given that we have $ available for crashing, which jobs would you crash and by how much? What is the least completion time of the project?
c Construct an LP model to answer part b You must define your variables clearly, write out the constraints and the objective function.