Question: Consider the project network given below: The data for normal times, crash times, and crashing costs are given as follows: Let ( T
Consider the project network given below:
The data for normal times, crash times, and crashing costs are given as follows:
Let T represent the earliest completion time of the project.
a Determine the maximum and the minimum value of T
b Set up the linear program to solve the CPM problem if the project is to be completed in days at minimum cost.
c Given the overhead costs as $ per day, determine the optimal duration of the project in terms of both the crashing and the overhead costs by direct enumeration method.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
