Question: Consider the project network given below: Numbers along the arcs represent: crash time ( days ) , normal time ( days ) per unit cost

Consider the project network given below:
Numbers along the arcs represent: crash time (days), normal time (days) per unit cost of crashing ($). Note: jobs A and B cannot be crashed.
(a) Use the direct enumeration method to determine the least cost crashing schedule that will meet the project deadline of 20 days. What is the total crashing cost?
(b) Given that we have $50 available for crashing, which jobs would you crash and by how much? What is the least completion time of the project?
(c) Construct an LP model to answer part (b). You must define your variables clearly, write out the constraints and the objective function.
 Consider the project network given below: Numbers along the arcs represent:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!