Question: Consider the project network given in the figure below where the name of the activity and its expected duration (in weeks) are shown on the

Consider the project network given in the figure

Consider the project network given in the figure below where the name of the activity and its expected duration (in weeks) are shown on the arcs. Use CPM to find the critical path by using expected task durations. F: 7 4 6 C: 6 1: 8 G: 6 A: 8 D: 5 2 7 J: 9 B: 5 H: 4 E: 7 The expected latest times for nodes 2 and 3 are respectively): O a. 8 and 5 O b. 8 and 22 OC 10 and 22 O d. 10 and 14 O e. None of these