Question: Consider the project network given in the figure below where the name of the activity and its expected duration in weeks) are shown on the

Consider the project network given in the figure

Consider the project network given in the figure below where the name of the activity and its expected duration in weeks) are shown on the arcs. Use CPM to find the critical path by using expected task durations. F: 7 C: 6 1: 8 G: 6 A: 8 D: 5 1 2 5 7 J: 9 8 B: 5 H: 4 3 E: 7 The total float of activity H is: O a. 12 O b.5 O c. 7 O d. 2 O e. O