Question: Question 4. Consider the project network given in the below figure where the expected duration and the variance (in parenthesis) values of activities are shown

Question 4. Consider the project network given in the below figure where the expected duration and the variance (in parenthesis) values of activities are shown on the arcs. Answer questions a-e. Show your work. (4 points each) 18 (2) 2 8(1) 913) 7 (21 20(4) 1 6 (2) 6(1) 512) 7121 1014) 12 (1) 7 (2) 6 a. What is the expected earliest time for event 7? b. What is the expected latest time for event 5? c. What is the free float for activity (6,8)? d. Assuming that activities are independent and that the central limit theorem applies, what is the probability that event 7 will take place on the 33 day or earlier
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
